Part B4 Fire-fighting water servicesPart B4 Fire-fighting water services
This Part sets out requirements for any part of a fire-fighting water service from the point of connection or other acceptable source(s) of supply to the fire-fighting equipment, including hydrants, hose reels, sprinkler services, automatic fire suppression systems and wall drencher systems.
Objectives
B4O1
Objective
2019: BO4
Functional Statements
B4F1
Fire-fighting water supply
2019: BF4
Performance Requirements
B4P1
Flow rate and pressure
2019: BP4.1
B4P2
Access and isolation
2019: BP4.1
B4P3
Fire-fighting water storage
New for 2022
B4P4
Uncontrolled discharge
2019: BP4.1
Deemed-to-Satisfy Provisions
B4D1
Deemed-to-Satisfy Provisions
2019: B4.1
B4D2
General requirements
2019: B4.2
B4D3
Fire sprinkler systems
New for 2022
B4D4
Fire hydrants
New for 2022
B4D5
Fire hose reels
New for 2022
B4D6
Bushfire prone areas
New for 2022
NCC Volumes One and Two deal with a number of areas of on-site construction which are relevant to fire-fighting water services. These include, but may not be limited to, those listed in Table B4.
Item | NCC Volume One Class 2 to 9 buildings | NCC Volume Two Class 1 and 10 buildings |
---|---|---|
Excavations for pipework adjacent to a building and footings | B1 Structural provisions | H1 Structure |
Termite management for attachments to buildings and penetrations through a slab | B1 Structural provisions | H1 Structure |
Penetrations for pipework through a vapour barrier | B1 Structural provisions | H1 Structure |
Pipework in timber bearers and joists of solid timber or engineered wood products | B1 Structural provisions | H1 Structure |
Fittings, fixtures and pipework installations in steel framed construction | B1 Structural provisions | H1 Structure |
Penetrations through a fire-resisting wall or floor | C1 Fire resistance Performance Requirements and C4 Protection of openings | H3 Fire safety |
Fixtures and fittings in a wet area | F2 Wet areas and overflow protection | H4 Health and amenity |
Service pipework external to the building and penetrations through roof cladding in a bushfire prone area | G5 Construction in bushfire prone areas | H7 Ancillary provisions and additional construction requirements |
Flues, chimneys, pipes, gas storage, domestic fuel tanks, cooling or heating appliances or other services | C4 Protection of openings | H3 Fire safety |