TAS Part I15 Premises for lead processingTAS Part I15 Premises for lead processing
This Part contains additional requirements for premises used for lead processing.
Every part of a lead processing area must be not less than 2.7 m in height—
Any areas in which dust-forming lead particles are manipulated, moved or treated must be served by a mechanical exhaust ventilation system capable of safely and effectively collecting all dust.
Where any process of pasting of electric accumulator plates or drying of paste plates, or melting down of pasted plates or of formation with tacking in the electric accumulator industry or of manipulation of dry oxide or lead, is to be carried out in the same room as any other lead process, the process of pasting, drying, melting, formation or manipulation must be isolated from one another and from any other lead process—
The racks or shelves provided in any drying room must be not more than 2.6 m from the floor nor more than 650 mm in width except that, in the case of racks or shelves set or drawn from both sides, the total width must not exceed 1.3 m.
Washing facilities served with running hot and cold water for the use of all employees engaged in a lead process must be provided consisting of—
In every work place in which lead is processed there must be provided two suitable furnished change rooms for the use of employees as follows—