TAS Part I15 Premises for lead processing

TAS Part I15 Premises for lead processing

Introduction to this Part

This Part contains additional requirements for premises used for lead processing.

Deemed-to-Satisfy Provisions

NCC Blurbs

(1) This Part is applicable to every building in which lead processes are used.

(2) Premises used for lead processing must—

  1. provide for the safety and comfort of workers; and
  2. be constructed in a manner that will minimise the lodgement of dust and must be capable of being flushed with water.
NCC Title

Application of Part

NCC State
TAS
NCC SPTC Current
Application of Part
NCC Blurbs

(1) The floor of every work place where a lead process is used must be—

  1. so constructed of concrete or other suitable material as to be smooth and impervious to fluids; and
  2. graded and properly drained to permit flushing with water.

(2) The mater of which the floor is constructed must be applied to the walls to a height of not less than 75 mm in such a fashion that the angle between the walls and the floor is coved for easy cleaning.

NCC Title

Floors

NCC State
TAS
NCC SPTC Current
Floors
NCC Blurbs

Every part of a lead processing area must be not less than 2.7 m in height—

  1. where a ceiling is provided, measured from the floor to the ceiling; or
  2. where a ceiling is not provided, measured from the floor to the lowest part of the roof.
NCC Title

Height of lead processing areas

NCC State
TAS
NCC SPTC Current
Height of lead processing areas
NCC Blurbs

(1) In every lead processing area there must be not less than 14 m3 of air space for each person employed therein, and in the calculation of such space the maximum height taken must be not greater than 4.2 m.

(2) The total floor space for the persons employed in such area, exclusive of space used for storage, must be not less than 3.3 m2 for each person so employed.

NCC Title

Air space and floor space

NCC State
TAS
NCC SPTC Current
Air space and floor space
NCC Blurbs

(1) The inner surfaces of the walls of every lead processing area must be of a smooth material impervious to fluids and must not contain any projections on which dust may lodge.

(2) The interior construction of the ceiling or roof must, so far as is practicable, be such that dust will not settle on it.

NCC Title

Interior of lead processing areas

NCC State
TAS
NCC SPTC Current
Interior of lead processing areas
NCC Blurbs

Any areas in which dust-forming lead particles are manipulated, moved or treated must be served by a mechanical exhaust ventilation system capable of safely and effectively collecting all dust.

NCC Title

Dust collection

NCC State
TAS
NCC SPTC Current
Dust collection
NCC Blurbs

Where any process of pasting of electric accumulator plates or drying of paste plates, or melting down of pasted plates or of formation with tacking in the electric accumulator industry or of manipulation of dry oxide or lead, is to be carried out in the same room as any other lead process, the process of pasting, drying, melting, formation or manipulation must be isolated from one another and from any other lead process—

  1. by a partition extending from the floor to the ceiling in the case of a room having a ceiling not more than 3.6 m in height, or to a height of 2.7 m in any other case; or
  2. by some other suitable method.
NCC Title

Isolation of certain processes

NCC State
TAS
NCC SPTC Current
Isolation of certain processes
NCC Blurbs

The racks or shelves provided in any drying room must be not more than 2.6 m from the floor nor more than 650 mm in width except that, in the case of racks or shelves set or drawn from both sides, the total width must not exceed 1.3 m.

NCC Title

Drying room shelves

NCC State
TAS
NCC SPTC Current
Drying room shelves
NCC Blurbs

Washing facilities served with running hot and cold water for the use of all employees engaged in a lead process must be provided consisting of—

  1. one washbasin for each 5 employees, or part thereof; and
  2. one shower bath for each 8 employees, or part thereof.
NCC Title

Washing facilities

NCC State
TAS
NCC SPTC Current
Washing facilities
NCC Blurbs

In every work place in which lead is processed there must be provided two suitable furnished change rooms for the use of employees as follows—

  1. one of the change rooms must be used for taking off, storing, and putting on of the street clothing of employees; and
  2. the other of the change rooms must be used for taking, storing, and putting on of overalls or other clothing work in any work room; and
  3. each change room must be so constructed and situated as to prevent the entry into the room of dust and fumes generated in a work room; and
  4. each change room must be in close proximity to the washing facilities required in TAS I15D9.
NCC Title

Change rooms

NCC State
TAS
NCC SPTC Current
Change rooms