TAS Part I13 Premises for production of processing of isocyanates
Introduction to this Part
This Part contains additional requirements for premises used for the production of processing of isocyanates.
Deemed-to-Satisfy Provisions
NCC Blurbs
(1) This Part is applicable to every building in which isocyanate production or processing is undertaken.
(2) Premises for production or processing of isocyanates must—
- provide for the safety and comfort of workers; and
- be constructed in a manner that will avoid the spread of fire within the building and to other buildings.
NCC SPTC Current
Application of Part
NCC ID
_2849527d-56d7-4cbb-b555-52aaacbb131d
Building Classes
1a,1b,10a,10b,10c
NCC Blurbs
Work places in which an isocyanate industry is carried out must be divided into the following divisional areas:
- Administration and staff amenities.
- Workshop.
- Bulk stores.
- Curing room.
- Processing plant.
- Raw materials plant.
- Manufacture.
NCC SPTC Current
Areas of work places
NCC ID
_39510e46-f7b5-4515-ba68-67dfd8838dca
Building Classes
1a,1b,10a,10b,10c
NCC Blurbs
(1) Each of the divisional areas required by TAS I13D2 other than the administration and staff amenities building, must be—
- separated from each of the other divisional areas by means of an impervious wall with an FRL of not less than 120/120/120; or
- separated from all other buildings by a clear space of not less than 6 m.
(2) Notwithstanding the distance requirements of (1), bulk stores of polyols and bulk stores of isocyanates must comply with the requirements of the Work Health and Safety Act.
NCC Title
Separation from other areas and buildings
NCC SPTC Current
Separation from other areas and buildings
NCC ID
_39e90db4-252c-44b3-ba5f-50d46c598c93
Building Classes
1a,1b,10a,10b,10c
NCC Blurbs
The building must be of single storey construction.
NCC SPTC Current
Rise in storeys
NCC ID
_58801804-ff49-4e5e-8f54-02fc48a12991
Building Classes
1a,1b,10a,10b,10c
NCC SPTC Current
Maximum floor areas
NCC ID
_70ed563c-19ac-466d-9c75-aa47f74d8422
Building Classes
1a,1b,10a,10b,10c
NCC Blurbs
(1) Every building and divisional area of a work place must have not less than 2 exits for escape purposes.
(2) The number and location of the exits must be such that any point on the floor is not more than 20 m from one of the exits.
(3) Only exits with vertically hinged swinging doors may be considered as exits for the purposes of this clause.
NCC SPTC Current
Required exits
NCC ID
_64bb0a3a-fbb6-4654-bd5e-29f493d77d6b
Building Classes
1a,1b,10a,10b,10c
NCC Blurbs
(1) A bulk store for polyols must be constructed from non-combustible materials and have a smooth impervious concrete floor and it must protect the polyols from direct exposure to the sun’s radiation.
(2) A bulk store for isocyanates must—
- be constructed from non-combustible materials, have a smooth impervious concrete floor, and must protect the isocyanate containers from direct exposure to the sun; and
- if it is used for the storage of either TDI or HDI and is not an open sided building, be fitted with mechanical ventilation so that the TLV is not exceeded at any time provided that the ventilation must provide not less than 6 air changes per hour.
(3) The area around both a polyol bulk store and an isocyanate bulk store must be bunded, the bund or bunds must ensure separation of the polyol and isocyanate areas and each bund must have a capacity of 10% more than the storage capacity of the largest tank it protects.
NCC Title
Bulk stores for polyols and isocyanates
NCC SPTC Current
Bulk stores for polyols and isocyanates
NCC ID
_d5d10039-58e4-4d11-9441-6f874dad6957
Building Classes
1a,1b,10a,10b,10c
NCC Blurbs
The curing room for the storage of newly produced flexible polyurethane foam must be constructed of non-combustible materials with a smooth impervious concrete floor and fitted automatic fire vents in the roof.
NCC SPTC Current
Curing room
NCC ID
_0d8b34a6-6826-434c-849e-ee6815d56e7d
Building Classes
1a,1b,10a,10b,10c